CEB Press design sprint: (incorporated here: http://opensourceecology.org/wiki/File:CEB_Press_1708_Frame_middle_module.fcstd),
Power Cube design sprint: (http://opensourceecology.org/wiki/File:PC_1708_coupler.fcstd, http://opensourceecology.org/wiki/File:PC_1708_5-8_coupler.fcstd, http://opensourceecology.org/wiki/File:PC_1708_5-8_9spline_coupler.fcstd)
August 5: Power Cube Design Sprint. (6hrs)
August 4: Reviewed the D3D BOM (3hrs)
July 30: Converted CEBPress Frame MidPlate to DXF. (4hrs)
July 22: CEB Press Design Sprint. Worked on re-positioning holes on the Mid Plates of the Frame (3.5hrs), observed sprint on Filament Extruder(3hrs)
These tasks span two weeks but I've ended up lumping them into one timesheet.