• 2.1 hr - Nov 29, 2025
    Max2

    Morning: 1:45pm-2:45pm

    Helped Ethan install bathroom vent fan

    Afternoon: 4pm-5:05pm

    Helped Ethan install bathroom vent fan

  • 5.4 hr - Nov 28, 2025
    Max2

    Morning: 10:00am-1:00pm

    Removed unnecessary electric box from old position

    Installed additional wall studs in bathroom 1 and 2 to mount future divider walls/pocket doors

    Helped Ethan with some electric work

    Afternoon: 2:55pm-5:20pm

    Helped James move heavy items out of storage

  • 1 hr - Nov 26, 2025
    Max2

    Afternoon: 2:30pm-3:30pm

    Cleaned out leftover insulation & tools to prepare for drywall installation

    Started preparing installation of Minisplit heat pump

  • 4.8 hr - Nov 25, 2025
    Max2

    Morning: 10:20am-12:05pm

    Installed ceiling supports for drywall on short walls

    Afternoon: 1:25pm-4:30pm

    Installed ceiling supports for drywall on interior walls

    Finished all the insulation we aren't blocked on (by minisplit, breaker panel install)

    Installed vanity light blocking

  • 6.3 hr - Nov 24, 2025
    Max2

    Morning: 10:30am-1:25pm

    Installed some electric boxes in ceiling

    Installed ceiling supports for drywall on short walls

    Afternoon: 2:05pm-5:30pm

    Finished bio digester cabin roof

    Finished ceiling insulation

    Continued on wall insulation

  • 5.8 hr - Nov 21, 2025
    Max2

    Morning: 10:15am-12:20pm

    Tried settling bio digester cabin walls with ratchet straps

    Installed remaining ceiling insulation

    Afternoon: 1:15pm-5pm

    Installed wall insulation

  • 5.5 hr - Nov 20, 2025
    Max2

    Morning: 10:50am-1:00pm

    Built & installed roof gutter mesh lath

    Afternoon: 2:00pm-5:20pm

    Continued bio digester cabin build

  • 6.7 hr - Nov 19, 2025
    Max2

    Morning: 10:00am-1:18pm

    Built bio digester cabin foundation

    Transported tools to FeF

    Afternoon: 2:35pm-6:00pm

    Put up bio digester cabin (70% complete?)

  • 5.8 hr - Nov 18, 2025
    Max2

    Morning: 10:00am-12:05pm

    Finished shingle install! Hallelujah!

    Cleaned up & organized build site

    Afternoon: 1:30pm-5:15pm

    Installed drip cap L-bracket on front veranda

    Installed 1x8 white trim over front veranda

    Installed vertical 1x6 white trim on front veranda sides

  • 6.1 hr - Nov 17, 2025
    Max2

    Morning: 10:00am-1:20pm

    Cut & installed remaining T1-11 on front porch inside walls

    Replaced split front porch plank

    Afternoon: 2:35pm-5:20pm

    Trimmed shingles to fit cedar trim

    Installed cedar shingle trim

    Installed shingles once again

  • 6.6 hr - Nov 14, 2025
    Max2

    Morning: 10:10pm-1:20pm

    Installed more shingles (1 week of shingles now!)

    Afternoon: 2:25pm-5:50pm

    Installed even more shingles

    Installed missing rear porch plank

  • 2.9 hr - Nov 13, 2025
    Max2

    Drove to Menards to pick up materials

  • 3.2 hr - Nov 13, 2025
    Max2

    Installed yet more shingles

    Added some more screws to sheet metal siding

    Took T1-11 siding off back porch walls (exterior) to make room for treated plywood

    Installed window trim spacer

    Started cutting J-channel for window

  • 3.2 hr - Nov 13, 2025
    Max2

    Installed more shingles

  • 7.7 hr - Nov 12, 2025
    Max2

    Morning: 10:00am-12:00pm

    Drove to FeF to get more materials (gravel, trim boards, interior doors)

    Afternoon: 12:00pm-5:40pm

    Spread more gravel on roof

    Installed more shingles

  • 5 hr - Nov 11, 2025
    Max2

    Morning: -

    Afternoon: 12:45pm-5:45pm

    Installed some more shingles

    Spread some more gravel on the roof

  • 2.3 hr - Nov 10, 2025
    Max2

    Afternoon: 2:55pm-5:15pm

    Continued installing front porch shingles (1/3 done)

    Spread gravel on roof (1/2 done)

  • 3.3 hr - Nov 10, 2025
    Max2

    Morning: 10-20am-1:40pm

    Installed front porch shingles

  • 3.3 hr - Nov 6, 2025
    Max2

    Afternoon: 2:30pm-5:50pm

    Installed sheet metal roofing on front porch

  • 2.8 hr - Nov 6, 2025
    Max2

    Morning: 10:20am-1:10pm

    Installed 6x6 posts on front porch