• 5.8 hr - Nov 21, 2025
    Max2

    Morning: 10:15am-12:20pm

    Tried settling bio digester cabin walls with ratchet straps

    Installed remaining ceiling insulation

    Afternoon: 1:15pm-5pm

    Installed wall insulation

  • 5.5 hr - Nov 20, 2025
    Max2

    Morning: 10:50am-1:00pm

    Built & installed roof gutter mesh lath

    Afternoon: 2:00pm-5:20pm

    Continued bio digester cabin build

  • 6.7 hr - Nov 19, 2025
    Max2

    Morning: 10:00am-1:18pm

    Built bio digester cabin foundation

    Transported tools to FeF

    Afternoon: 2:35pm-6:00pm

    Put up bio digester cabin (70% complete?)

  • 5.8 hr - Nov 18, 2025
    Max2

    Morning: 10:00am-12:05pm

    Finished shingle install! Hallelujah!

    Cleaned up & organized build site

    Afternoon: 1:30pm-5:15pm

    Installed drip cap L-bracket on front veranda

    Installed 1x8 white trim over front veranda

    Installed vertical 1x6 white trim on front veranda sides

  • 6.1 hr - Nov 17, 2025
    Max2

    Morning: 10:00am-1:20pm

    Cut & installed remaining T1-11 on front porch inside walls

    Replaced split front porch plank

    Afternoon: 2:35pm-5:20pm

    Trimmed shingles to fit cedar trim

    Installed cedar shingle trim

    Installed shingles once again

  • 6 hr - Nov 15, 2025
    Barry

    Worked on metal siding. J-Trim around windows, worked on back veranda walls.

  • 6.6 hr - Nov 14, 2025
    Max2

    Morning: 10:10pm-1:20pm

    Installed more shingles (1 week of shingles now!)

    Afternoon: 2:25pm-5:50pm

    Installed even more shingles

    Installed missing rear porch plank

  • 6.5 hr - Nov 13, 2025
    Barry

    Worked on metal siding and trim on veranda.

  • 2.9 hr - Nov 13, 2025
    Max2

    Drove to Menards to pick up materials

  • 3.2 hr - Nov 13, 2025
    Max2

    Installed yet more shingles

    Added some more screws to sheet metal siding

    Took T1-11 siding off back porch walls (exterior) to make room for treated plywood

    Installed window trim spacer

    Started cutting J-channel for window

  • 3.2 hr - Nov 13, 2025
    Max2

    Installed more shingles

  • 7.7 hr - Nov 12, 2025
    Max2

    Morning: 10:00am-12:00pm

    Drove to FeF to get more materials (gravel, trim boards, interior doors)

    Afternoon: 12:00pm-5:40pm

    Spread more gravel on roof

    Installed more shingles

  • 36 hr - Nov 12, 2025
    Eduardo

    Technical standards Documentation per component of irrigation system referenced on official hardware information.
    Documentation on limits and capacities of commercial automation systems.

  • 5 hr - Nov 11, 2025
    Max2

    Morning: -

    Afternoon: 12:45pm-5:45pm

    Installed some more shingles

    Spread some more gravel on the roof

  • 2.3 hr - Nov 10, 2025
    Max2

    Afternoon: 2:55pm-5:15pm

    Continued installing front porch shingles (1/3 done)

    Spread gravel on roof (1/2 done)

  • 3.3 hr - Nov 10, 2025
    Max2

    Morning: 10-20am-1:40pm

    Installed front porch shingles

  • 3.5 hr - Nov 7, 2025
    Barry

    1130a - 3p
    continued to work on finishing the verandas. Installed more T1-11 siding.

  • 1 hr - Nov 7, 2025
    Tom

    Marcin: "Hanger" files not downloading. Turned out that the files were missing from the "images" folder. Updated the files from Hetzner2 and tested to success.

  • 7 hr - Nov 6, 2025
    Barry

    10a - 1p
    2p - 6p
    Continued to work on Veranda on both the north and south end. Prep work for the siding such as metal siding end caps.

  • 3.3 hr - Nov 6, 2025
    Max2

    Afternoon: 2:30pm-5:50pm

    Installed sheet metal roofing on front porch

  • 2.8 hr - Nov 6, 2025
    Max2

    Morning: 10:20am-1:10pm

    Installed 6x6 posts on front porch

  • 6 hr - Nov 6, 2025
    Eduardo

    Cost of each material- Information refence

  • 3 hr - Nov 5, 2025
    Max2

    Afternoon: 2:50pm-5:50pm

    Replaced front porch boards under french door

    Lifted up all 3 front porch roof modules

    Fixed rear of all 3 front porch roof modules to house wall

  • 2.8 hr - Nov 5, 2025
    Max2

    Morning: 10:00am-12:45pm

    Carried gravel bags onto roof

    Shimmed & squared french door

  • 7 hr - Nov 5, 2025
    Barry

    10a - 1230p
    130p - 6p
    Set up for front veranda roof. worked on finishing panels on back veranda. Installed roof frame for front veranda.

  • 48 hr - Nov 5, 2025
    Eduardo

    8 days of work-
    Sunshade, Birdnet, Structures: Open Source Alternatives trough
    Bucky designs for structures, Less Material to More strength relationship.
    Sunshade design per line with mechanics to open and close.
    Birdnet analysis compared to bird laser for reducing cost and increasing efficiency.
    KW, Water cubic meter, reverse osmosis references in cost.
    Analysis per plant on each component of structures.

  • 6 hr - Nov 4, 2025
    Barry

    10a - 1p
    2p - 5p
    Worked on back veranda. Finished metal roofing and worked on some final wood paneling. Leveled front veranda deck to prepare for walls. Installed east walls and temporarily secured them. Set up roof frames and prepped for roof installation.

  • 3.5 hr - Nov 4, 2025
    Max2

    Afternoon

    Installed french door
    Leveled part of front porch a bit better to fit front porch wall
    Installed second front porch wall
    Carried all 3 front porch roof modules to front of building for installation

  • 2.2 hr - Nov 4, 2025
    Max2

    Morning

    * Added more screws to back porch sheet metal roof, was flapping in the wind
    * Started on french door installation
    * Installed tar flashing tape in french door frame

  • 2.1 hr - Nov 3, 2025
    Max2

    Afternoon: 3:55pm-6:00pm

    Installed back porch roof modules

    Installed back porch 4x4 post

    Installed back porch metal roofing

  • 4.3 hr - Nov 3, 2025
    Max2

    Morning: 10:25am-2:40pm

    Installed back porch walls

    Built back porch 2nd roof module

  • 7.5 hr - Nov 3, 2025
    Barry

    10a - 230p
    330 - 530p
    Worked on the back veranda decking, roof and walls. Put on metal roofing and support post.

  • 4.5 hr - Nov 1, 2025
    Max2

    Afternoon: 12:00pm-4:30pm

    Leveled, positioned, and fixed front porch beneath sliding doors

  • 2 hr - Nov 1, 2025
    Max2

    Morning: 10:00am-12:00pm

    Installed flashing tape on both sliding doors

    Sliding door flashing tape

    Built back veranda walls

  • 6 hr - Nov 1, 2025
    Barry

    10a - 11a meeting online in the morning.
    11a - 2p set up and frame, cut veranda decking
    lunch
    3p - 7p finished decking, built wall modules, modified jig, cut, started veranda roof frame

  • 3.4 hr - Oct 31, 2025
    Max2

    Afternoon: 3:35pm-7pm

    Finished back veranda deck

    Started back veranda wall frames

    Screwed in 2nd rear veranda door frame

  • 3.6 hr - Oct 31, 2025
    Max2

    Morning: 10:25am-2pm

    Finished 2nd window installation

    Window sealed with tar tape


    Build back veranda frame and installed planks

  • 8 hr - Oct 31, 2025
    Barry

    10a - 2p
    3p - 7p
    Built 2 back veranda modules deck. Built 2 walls. Roughed the deck into place.

  • 6.8 hr - Oct 30, 2025
    Max2

    Afternoon: 12:00pm-6:45pm

    Installed siding

    Metal siding

    Cut opening for east side windows

    Cut window holes

    Installed flashing tar tape on both window frames

    Window flashing tape

    Installed first window

    Window installed.jpg

    Started installation of second window

  • 2 hr - Oct 30, 2025
    Max2

    Morning: 10:00am-12:00pm

    Trimmed PV runners

    PV runners flush with cap

    Fixed up PV runner cap 2x4 on the 3rd module

    Folded up roof membrane at the south side to fit with PV runner cap 2x4s

    Wrapped & taped up end caps between modules

    Installed some 1x6 roof trim

  • 6.5 hr - Oct 30, 2025
    Barry

    11a - 4p
    5p - 630p
    prepared, cut and Installed metal siding all around the house up to the edges of where the verandas will be. reinforced trimming attachments on inside with OSB. Helped install the east windows.

  • 1 hr - Oct 29, 2025
    Barry

    Arrived 3:30pm - ended 7p. Got up to speed. Not fully effective as I worked with Solar panels because of instruction, but was able to help for a good hour. Then had to get oriented with next task. Started preparing for metal siding.

  • 3 hr - Oct 28, 2025
    Max

    First time using log

    Wrote my Written Application

  • 2 hr - Oct 26, 2025
    FelixMakori

    Completed and uploaded "Written Application."

  • 5 hr - Oct 26, 2025
    Eduardo

    Media,Pot,Reservoir system design references:

    Geometry & Spacing
    Design Loads
    Anchoring
    Benches / Racks
    Harvester Clearance
    Vibration & Sway
    Drainage & Recirculation water fluids
    Irrigation Manifold
    Materials & Corrosion
    Quality / Inspection

  • 5 hr - Oct 25, 2025
    Eduardo

    Geometry Design for Low Cost Growing Media

  • 6 hr - Oct 24, 2025
    Eduardo

    Blueberry System Limits: Design,Weight,form,size,shape.
    Slides in Work Doc

  • 2.5 hr - Oct 22, 2025
    Eduardo

    3D printers for Growing Media

  • 3 hr - Oct 21, 2025
    Eduardo

    Fluid Mechanics- Open Source: Media, Pots, Reservoirs, Water recycling

  • 7 hr - Oct 20, 2025
    Tom

    The redirect of the "root" OSE page that was solved yesterday quit working. After much troubleshooting, Marcin said he'd have the video updated so the redirect wouldn't be necessary.