Tom
8:00 meeting @ Hablab. Continued work on the compressed air distribution, finally got 3 bays working.
8:00 meeting @ Hablab. Continued work on the compressed air distribution, finally got 3 bays working.
Started work on hanger utilities. 9:00 Kickoff meeting @ Hablab. Returned to hanger, worked on air and electrical outlets. Made late night run to Menard's.
i built doors
Met Mark and asked for help with electrical setup in Hanger. Collected supplies and started running wires for bay receptacles.
Still composing lists for purchase. Reached end, gave to Marcin for review. Drove to St Jo Harbor Freight, Home Depot and Menard's for pickup.
Morning: 1:45pm-2:45pm
Helped Ethan install bathroom vent fan
Afternoon: 4pm-5:05pm
Helped Ethan install bathroom vent fan
Fetched computers for workshop. Spent the day working on lists of items necessary for connecting hanger with electricity, air and networking.
Morning: 10:00am-1:00pm
Removed unnecessary electric box from old position
Installed additional wall studs in bathroom 1 and 2 to mount future divider walls/pocket doors
Helped Ethan with some electric work
Afternoon: 2:55pm-5:20pm
Helped James move heavy items out of storage
Used skid steer and grader to smooth out "lumps" of clay between workshop and hanger. Poly line kinked in 2 places - applied covering and hose clamps. Fixed Roy's reciprocating saw. Made auger bit to drill hole to complete poly tube run into hanger.
Trenching from workshop to Learning Center to Hanger. Ran wires and tube for compressed air. Late night run to Menard's - filled trailer with insulation.
Afternoon: 2:30pm-3:30pm
Cleaned out leftover insulation & tools to prepare for drywall installation
Started preparing installation of Minisplit heat pump
Started and completed Apprenticeship "Wall Module Build".
Morning: 10:20am-12:05pm
Installed ceiling supports for drywall on short walls
Afternoon: 1:25pm-4:30pm
Installed ceiling supports for drywall on interior walls
Finished all the insulation we aren't blocked on (by minisplit, breaker panel install)
Installed vanity light blocking
Morning: 10:30am-1:25pm
Installed some electric boxes in ceiling
Installed ceiling supports for drywall on short walls
Afternoon: 2:05pm-5:30pm
Finished bio digester cabin roof
Finished ceiling insulation
Continued on wall insulation
Morning: 10:15am-12:20pm
Tried settling bio digester cabin walls with ratchet straps
Installed remaining ceiling insulation
Afternoon: 1:15pm-5pm
Installed wall insulation
Morning: 10:50am-1:00pm
Built & installed roof gutter mesh lath
Afternoon: 2:00pm-5:20pm
Continued bio digester cabin build
Morning: 10:00am-1:18pm
Built bio digester cabin foundation
Transported tools to FeF
Afternoon: 2:35pm-6:00pm
Put up bio digester cabin (70% complete?)
Morning: 10:00am-12:05pm
Finished shingle install! Hallelujah!
Cleaned up & organized build site
Afternoon: 1:30pm-5:15pm
Installed drip cap L-bracket on front veranda
Installed 1x8 white trim over front veranda
Installed vertical 1x6 white trim on front veranda sides
Morning: 10:00am-1:20pm
Cut & installed remaining T1-11 on front porch inside walls
Replaced split front porch plank
Afternoon: 2:35pm-5:20pm
Trimmed shingles to fit cedar trim
Installed cedar shingle trim
Installed shingles once again
Worked on metal siding. J-Trim around windows, worked on back veranda walls.
Morning: 10:10pm-1:20pm
Installed more shingles (1 week of shingles now!)
Afternoon: 2:25pm-5:50pm
Installed even more shingles
Installed missing rear porch plank
Worked on metal siding and trim on veranda.
Drove to Menards to pick up materials
Installed yet more shingles
Added some more screws to sheet metal siding
Took T1-11 siding off back porch walls (exterior) to make room for treated plywood
Installed window trim spacer
Started cutting J-channel for window
Installed more shingles
Morning: 10:00am-12:00pm
Drove to FeF to get more materials (gravel, trim boards, interior doors)
Afternoon: 12:00pm-5:40pm
Spread more gravel on roof
Installed more shingles
Technical standards Documentation per component of irrigation system referenced on official hardware information.
Documentation on limits and capacities of commercial automation systems.
Morning: -
Afternoon: 12:45pm-5:45pm
Installed some more shingles
Spread some more gravel on the roof
Afternoon: 2:55pm-5:15pm
Continued installing front porch shingles (1/3 done)
Spread gravel on roof (1/2 done)
Morning: 10-20am-1:40pm
Installed front porch shingles
1130a - 3p
continued to work on finishing the verandas. Installed more T1-11 siding.
Marcin: "Hanger" files not downloading. Turned out that the files were missing from the "images" folder. Updated the files from Hetzner2 and tested to success.
10a - 1p
2p - 6p
Continued to work on Veranda on both the north and south end. Prep work for the siding such as metal siding end caps.
Afternoon: 2:30pm-5:50pm
Installed sheet metal roofing on front porch
Morning: 10:20am-1:10pm
Installed 6x6 posts on front porch
Cost of each material- Information refence
Afternoon: 2:50pm-5:50pm
Replaced front porch boards under french door
Lifted up all 3 front porch roof modules
Fixed rear of all 3 front porch roof modules to house wall
Morning: 10:00am-12:45pm
Carried gravel bags onto roof
Shimmed & squared french door
10a - 1230p
130p - 6p
Set up for front veranda roof. worked on finishing panels on back veranda. Installed roof frame for front veranda.
8 days of work-
Sunshade, Birdnet, Structures: Open Source Alternatives trough
Bucky designs for structures, Less Material to More strength relationship.
Sunshade design per line with mechanics to open and close.
Birdnet analysis compared to bird laser for reducing cost and increasing efficiency.
KW, Water cubic meter, reverse osmosis references in cost.
Analysis per plant on each component of structures.
10a - 1p
2p - 5p
Worked on back veranda. Finished metal roofing and worked on some final wood paneling. Leveled front veranda deck to prepare for walls. Installed east walls and temporarily secured them. Set up roof frames and prepped for roof installation.
Afternoon
Installed french door
Leveled part of front porch a bit better to fit front porch wall
Installed second front porch wall
Carried all 3 front porch roof modules to front of building for installation
Morning
* Added more screws to back porch sheet metal roof, was flapping in the wind
* Started on french door installation
* Installed tar flashing tape in french door frame
Afternoon: 3:55pm-6:00pm
Installed back porch roof modules
Installed back porch 4x4 post
Installed back porch metal roofing
Morning: 10:25am-2:40pm
Installed back porch walls
Built back porch 2nd roof module
10a - 230p
330 - 530p
Worked on the back veranda decking, roof and walls. Put on metal roofing and support post.
Afternoon: 12:00pm-4:30pm
Leveled, positioned, and fixed front porch beneath sliding doors
Morning: 10:00am-12:00pm
Installed flashing tape on both sliding doors
Sliding door flashing tape
Built back veranda walls
10a - 11a meeting online in the morning.
11a - 2p set up and frame, cut veranda decking
lunch
3p - 7p finished decking, built wall modules, modified jig, cut, started veranda roof frame
Afternoon: 3:35pm-7pm
Finished back veranda deck
Started back veranda wall frames
Screwed in 2nd rear veranda door frame